A short post after a long day. Also a productive day.

After relative quiet on site–over the weekend it was just me and Jesse, with Matt coming out a few times as well–we had a hive of activity today. Jesse kept cranking away on the brackets, while Alexi and his crew got started on the roof.

The SIPs panels arrived on two semis first thing in the morning. From there half the crew did some final prep (I even got in on the action again, using a router to detail the beams) while the other guys organized 45 panels into the right order. At up to 700 pounds each, this is no small trick.

We rented a big crane for the day to get panels into the most difficult corner of the house. Good call. And while the crew hoped to get a few more panels installed, we covered our daughter’s room, the guest room, bathroom and a bit more.

Starting a SIPs roof is a bit like starting a tile job. The first few pieces take longer. Why? Well the first panels set the geometry and rhythm for the rest of the project. If you’re off a bit on the first few, you’ll be off a lot by the last few.

Tomorrow should see big progress. I’ll be back at work, but it should be fun to swing by afterwards. The crew expects to have most of the house covered by the end of the day.